Starting with Sprint - The First Prefabricated T-Beam of Sichuan Huili Project of Fourth Company Successfully Erected
On February 24th, the installation of the first prefabricated T-beam of the Zhujing Township Bridge in Sichuan Huili Project of the Fourth Company was completed, and the construction of the upper structure of the project officially began.
The prefabricated T-beam that has been erected this time is 20 meters long, 1.8 meters wide, 1.5 meters high, and weighs approximately 50 tons. To ensure smooth installation, the project department has developed a detailed installation plan and conducted trial operation inspections on the lifting crane, beam transport gun truck, and bridge erecting machine. The successful installation of this T-beam provides an effective demonstration for subsequent construction and accumulates successful experience.
The Sichuan Huili project will continue to forge ahead, carry forward the spirit of overcoming difficulties, and make every effort to complete the construction task goals.